PROJECT DAWN 2015

Project Dawn, is a three-year development project worth $1.2 billion that includes the construction of a pipeline network to deliver natural gas to the Escravos – Lagos Pipeline System (ELPS), which was designed and constructed under the supervision of Penspen more than two decades ago. Project Dawn introduced 250mmscf/d of natural gas under the Gas Sale and Purchase Agreement (GSPA) between Sirius Oilfield Support Services Ltd and Nigerian Gas Company (NGC) a Subsidiary of NNPC. The project include an evaluation of the OML-122 field development, subsea gas pipeline and onshore central processing facility. The project study seek to determine the extent of new pipeline and facilities required, and quantify the overall investment required for the project. The project includes workshops in Nigeria that cover the screening of options, as well as decision and risk analysis.

ALAKIRI ASSOCIATED GAS (AG) FLAREDOWN COMPRESSOR PROJECT

Client: Eroton Exploration and Production Company
Location: OML 18, Alakiri Field, Rivers State.
Scope: Installation and Management of two Associated Gas (AG) Compressors
Capacity/Flow Rate: 7MMscf/day each
Start Date: January 2021
Status: Ongoing

60 MAN HOUSE BOAT CONSTRUCTION

Client: Aiteo Energy Limited Location: Port Harcourt, Rivers State. Scope: Construction of one 40-Man Houseboat and 2 60-Man Houseboat Start Date: Status: Ongoing

Quick Facts


  • Study made with Paspen

  • $1.2 billion worth

  • 250mmscf/d of natural gas inteoduced


  • 200MW Capacity

  • 69 Million tones of coal concession

  • Cost USD 900 million

  • Production of 1 million metric tonnes

ALAKIRI ASSOCIATED GAS (AG) FLAREDOWN COMPRESSOR PROJECT

WELL INTERVENTION PROJECT

Client: Heritage Energy Operational Services Limited (HEOSL)
Location: OML 30
Scope: Slickline Operations involving acquisition of BHP data, Gas Lift Valve Change Out (GLVCO) and Tubing Integrity checks.
Start Date: July 2021
Status: Ongoing